If you are a director of a small or medium sized company, you may be faced with the question of determining what is a reasonable and acceptable level of remuneration for yourself as a director. Parry Field Lawyers provide legal advice for managing your company including payment of directors’ fees.

Read more

The New Zealand Government enacted the Construction Contracts Act 2002 to help sub-contractors get paid on time and without fuss for construction work and to enable fast resolution to disputes arising under construction contracts. Parry Field Lawyers provides assistance with making and defending claims under the Construct Contracts Act.

Does the Construction Contracts Act apply to me?

The Act applies to a wide range of construction work, namely:

  • Construction, installation, alteration, repair, restoration, maintenance, extension, demolition, removal, or dismantling of any building or other structure.
  • Installing roadways, pipelines, water mains, sewers, electricity, water, gas, or telephone reticulation.
  • Heating , lighting, air conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, security, and communications systems.
  • Any cleaning work carried out as part of the construction work.
  • Preparation for construction work such as site clearance, earth-moving, excavation, laying foundations; scaffolding.
  • Site restoration and landscaping, painting and decorating.

Making a Payment Claim

The parties to a construction contract are free to agree between themselves on:

  1. The number of progress payments under the contract.
  2. The gap between those payments.
  3. The amount of each of those payments.
  4. The date when each of those payments becomes due.

Where the contract does not address these issues, a contractor who carries out construction work for another person is entitled to issue monthly ‘payment claims’ for work done during that month. A payment claim must either be disputed or paid by the customer within the time period agreed for a response in the contract, by default this is 20 working days.

A payment claim must:

  1. Be in writing.
  2. Contain sufficient details to identify the construction contract to which the progress payment relates
  3. Identify the construction work and the relevant period to which the progress payment relates.
  4. Indicate a claimed amount and the due date for payment.
  5. Indicate the manner in which the payee calculated the claimed amount.
  6. State that it is made under the Construction Contracts Act.

If a payment claim is to be given to a residential occupier of a property, it must include a notice in a form prescribed by the Act setting out what the residential customer must do in response to the payment claim.

Payment Schedules

If the customer wants to dispute the payment claim, they must object to the payment claim by giving the contractor a ‘payment schedule’ in writing identifying the payment claim to which it relates and indicating what amount the customer is prepared to pay (which can be nothing). The amount the customer is willing to pay is called the ‘scheduled amount’.

If the scheduled amount is less than the claimed amount, the payment schedule must indicate:

  1. How the customer calculated the scheduled amount.
  2. The customer’s reason or reasons for the difference between the scheduled amount and the claimed amount.
  3. In a case where the difference is because the customer is withholding payment on any basis, the customer’s reason or reasons for withholding payment.

If the customer does not give the contractor a payment schedule by the deadline agreed in the contract, the customer becomes liable to pay the full amount claimed in the payment claim and the contractor may recover it from the customer by court proceedings, which cannot easily be defended by the customer.

Adjudication

If the customer issues a payment schedule within the time limit disputing all or part of the claimed amount, the contractor can refer the matter as a dispute for adjudication under the Construction Contracts Act.

The Act provides an adjudication process that enables a contractor to quickly get a decision on how much is owed by the customer. After the adjudicator is appointed, the contractor has five days to provide information in support of their claim. The customer then has five working days to respond. The Adjudicator must then issue a decision within 30 working days.

An adjudicator’s decision can be enforced in the District or High Court in the same that a judgment of those courts can be enforced.  This means the adjudication process can be an effective way to obtain quick payment for work.

 

This article is not a substitute for legal advice and you should talk to a lawyer about your specific situation. If we can assist in any way please do not hesitate to contact Paul Cowey at Parry Field Lawyers (348-8480), paulcowey@parryfield.com 

In November 2009, Parliament implemented significant changes to the claim process in New Zealand’s District Courts.  The aim of the changes is to simplify the claim process, reduce the cost of litigation, and bring relevant information to light quickly to promote settlement discussions.

Read more

New Zealand law imposes time limits on suing other people.  These time limits often trip people up, and prevent them bringing what would otherwise have been strong claim. Parry Field Lawyers provide legal advice on a range of commercial matters include disputes and court proceedings.
Read more

“An ounce of prevention is worth a pound of cure.”

For most small businesses, your lease will be one of your most important contractual documents.  Get it wrong and the profitability of your business may be seriously affected.  Even so it is common for business to sign up agreements to lease without getting legal help. The lawyers at Parry Field have considerable experience in helping tenants to negotiate lease terms that fairly protect the tenant from undue risk and cost.
Read more

Many businesses operate without clear written terms and conditions of trade.  Services are provided and goods are supplied without any clear record of who will cover the cost if something goes wrong. Taking the time to prepare clear and reasonable terms and conditions of trade can help ensure that your business risk is identified and properly managed.  The team at Parry Field Lawyers are experienced at drafting terms of trade to ensure that risks associated with your work are clearly identified and allocated.

Read more

Many small businesses struggle with cashflow due to slow paying customers. Often customers choose to move bills from small businesses to the back of the pile, and pay other bills first.  Well drafted terms and conditions of trade can turn customer behaviour around so they pay your bills first.  The team at Parry Field Lawyers are experienced in drafting terms and conditions of trade that can help improve cashflow. Read more

Business is hard enough work without having to worry about how to collect unpaid debt. Parry Field Lawyers offer legal assistance on a range of commercial matters including streamlining your debt collection process.